The Zhenhai POX Project of Zhenhai Refinery for modifying the structure of hydrogen production raw material, for which the company is the EPC contract, was capped a few days ago, which laid down a solid foundation for the installation of non-standard equipment (including gasifier) in this area.
The construction of the gasification frame of POX project started in October last year. The post pouring of concrete structure started on March 5 this year and the pouring of platform floor 1 was begun on March 16. After that, one platform floor was poured every half a month in average. The platform floor 8 poured on July 11 was also the last layer of gasification frame, with a pouring area of 775 m2 and concrete quantity of 220 m3.