Recently, the company won the bid section III of 2017 shut-down maintenance project of Ningbo Zhongjin Petrochemical by its good credit and rich experience in construction technology and management.

The main works quantity of bid section III involves the static and dynamic equipment, process pipelines, electrics, instruments, civil works, anti-corrosion works and insulation works located within the area of reforming unit and No. 4 integrated unit. The reforming unit has 133 maintenance items and 16 technical modification items. The No. 4 integrated unit has 184 maintenance items and 7 technical modification items.

It’s learned that the maintenance project is planned to last 26 days starting from August 30 and terminated on September 25 when it’s finished for delivery.