SNEC Ningbo Tianyi Fabrication Branch Handover Maoming Petrochemical Equipment Fabrication Project Smoothly

On December 3, 12 sets of equipment were shipped at Zhenhai Cargo Wharf smoothly, which was undertook by Ningbo Tianyi Fabrication Branch for 1.5million t/y continuous catalytic reforming plant in Maoming Petrochemical Branch and 200,000 t/y ethylene oxide plant in Maoming Petrochemical Nanhai Fine Chemical Co., Ltd.

The two projects have 12 sets of equipment in total with more than 300t of total weight, in which, the maximum diameter of the rich absorption water flash drum is 4 meters and the length is 10m. The longest length of glycol reactor is 48.9m and the diameter is 0.6m.

It is said that the 12 sets of equipment of this project will take 7 days to deliver at Maoming Petrochemical project site.